Before construction begins, Ghana’s Environmental Protection Agency Act, 1994 (Act 490) mandates that certain environmental requirements be met to safeguard ecological integrity. Here’s what applicants need to fulfill:
1. Apply for an Environmental Permit
An Environmental Permit from the EPA is mandatory for projects with potential environmental impacts. The application should include detailed project information and estimated impacts.
2. Conduct an Environmental Impact Assessment (EIA)
Many projects require an EIA conducted by qualified consultants to assess environmental and social impacts. A Scoping Report, outlining major environmental concerns, is submitted first, followed by a comprehensive EIA.
3. Submit an Environmental Management Plan (EMP)
Approved projects must have an EMP outlining strategies to manage and mitigate risks during construction, covering waste, air quality, and health and safety protocols.
4. Conduct Public Consultations
Act 490 requires public consultations for projects with significant community impacts, incorporating public concerns into planning and design.
5. Obtain an Environmental Certificate
Once the EIA and EMP are approved, an Environmental Certificate is issued, granting legal clearance for construction to proceed.
6. Annual Environmental Audits and Compliance Reporting
Submit annual environmental audit reports to the EPA, detailing waste management, air quality, noise levels, and adherence to environmental standards.
7. Monitor and Report Environmental Impacts
During construction, monitor and report on air, water, and soil quality, as well as biodiversity impacts. The EPA requires records of compliance with the EMP.
8. Develop a Waste Management Plan
A Waste Management Plan must cover collection, storage, and disposal of all construction waste, including hazardous materials.
9. Health and Safety Plan
Ensure a Health and Safety Plan is in place, covering safety protocols, hazard management, and emergency procedures.
10. Rehabilitation and Restoration Plan
For projects that disturb land, a Rehabilitation Plan should cover actions to restore and rehabilitate the site after completion.
11. Buffer Zone Compliance
Adhere to buffer zones for ecologically sensitive areas, such as wetlands and protected areas, as required by the EPA.
Failure to comply with these requirements can result in fines, project suspension, or permit revocation. Following these steps protects the environment and ensures sustainable project development.